![]() Move start of remaining parts before status date forward to status date.Move start of remaining parts back to status date.Move end of completed parts after status date back to status date.In my Options > Calculation I generally have the following set: How do you handle this? My "Hack" Workaround Project doesn't update the tracking Gantt, so you can't see that the project is "slipping". The problem occurs when I'm updating the % Complete, but a task that was supposed to be complete (or in progress) has not been started yet, so I leave it at 0% Complete. Once I've set up my baseline, I like to use the Tracking view to see schedule slippage (ie: is a project going to be "late"?).